|
1. ISRA
COMPLIANCE (NJDEP) - TSCA COMPLIANCE (USEPA)
SITE / LOCATION: Pharmaceutical Manufacturer, Morris
County, New Jersey
PROJECT HIGHLIGHTS:
·
Saved client at least $2.5 million and eliminated
liability associated with off-site waste disposal by negotiating
risk-based approval for capping PCB-impacted soil with concentrations
greater than 100 ppm on-site. This
remedy is the first approval of its kind in the nation under USEPA PCB
regulations (the Amega-rule)
promulgated in August 1998
·
Designed cap for in-place remediation of PCB-impacted
soil to satisfy various regulatory requirements, wetlands issues, and
proposed commercial redevelopment of the site
·
Reduced remedial requirements by successfully
demonstrating to the NJDEP that ground water was not impacted by
PCB-impacted soils
·
Obtained NFA letters for 21 Areas of Concern in 18 months
·
Minimized remedial action in wetlands by performing an
ecological evaluation
·
Conducted local study of hydrogeology and upgradient
off-site sources of ground water contamination with chlorinated solvents
and demonstrated that on-site chlorinated solvents originated from an
off-site source. Received a
No Further Action determination from the NJDEP
·
Repackaged
Preliminary Assessment Report to comply with ISRA regulations
PROJECT SUMMARY:
TRC Raviv prepared a Remedial
Action Selection Report and Remedial Action Workplan for the clients
facility in Morris County, New Jersey.
Following negotiations with regulatory agencies, TRC Raviv successfully
obtained Remedial Action Workplan approval, which will transform the
inactive, contaminated site to an environmentally sound and economically
viable property.
A former landfill at the
site was impacted with PCB concentrations as high as 1,300 ppm.
TRC Raviv assessed the extent of environmental impacts to ground water,
wetlands and soil, and demonstrated to the NJDEP that there was no impact
to ground water from PCB-impacted soils.
As a result, costly ground water monitoring and remediation
requirements were not required. TRC Raviv performed an ecological evaluation and successfully
demonstrated to the NJDEP that PCBs in the wetlands should remain in
place, thereby further reducing remediation costs.
Based on the Remedial
Action Selection Report and Remedial Action Workplan, capping was approved
by the NJDEP and USEPA as the appropriate remedial approach for the site.
USEPA approval to cap PCB-containing soil and waste is required
under the Federal Toxic Substance Control Act (TSCA).
TRC Raviv's
design of the capping system coordinated complicated state and federal
environmental and engineering requirements with proposed commercial
redevelopment plans for the site.
TRC Raviv
received the first USEPA risk-based draft approval under the new Federal
Toxic Substance Control Act regulations for leaving PCB-impacted soil with
concentrations greater than 100 ppm on-site after instituting an
engineering control. This
approval saved the client at least $2.5 million in soil excavation and
disposal costs, and reduced the client’s future liability associated
with the off-site disposal of hazardous, TSCA-regulated waste.
The 5-acre cap is designed to be protective of
human health and the environment and to accommodate the proposed
redevelopment of the site. A
portion of the cap has been designed as a parking facility (asphalt cap),
with the remainder designed as a geotextile soil cap that will incorporate
the wetlands buffer zone. PCB-impacted
soil from a 0.5-acre portion of impacted wetlands will be excavated and
placed beneath the cap, followed by wetlands restoration.
Another aspect of this
project was to restructure a pre-existing Preliminary Assessment Report
and conduct supplemental soil and ground water remedial investigation
activities to facilitate the ISRA compliance process.
Within 18 months, a total of 21 areas of concern (AOCs), including
ground water contamination with chlorinated solvents, were issued No
Further Action (NFA) determinations by the NJDEP.
The ground water NFA was issued based on the submission of regional
information compiled by TRC Raviv, demonstrating an off-site source of the
trichloroethylene (TCE) detected on the client's
property.
Back
to Top
2.
ENCAPSULATION SYSTEM DESIGN - STORM WATER MANAGEMENT
SITE / LOCATION:
Scrap Metal Recycling Facility, Middlesex County, New Jersey
PROJECT HIGHLIGHTS:
- Environmental
investigations and remediation of soil and ground water
- Remedial
action plan includes installation of a low permeability, soil/bentonite
capping system over 2 acres of the 4- acre site, and a storm water
treatment system to treat all runoff
-
As part of the remedial design, the operations of the site were
re-configured to meet the requirements of the capping system and storm
water management plan
-
The design of the remedial action involved simultaneous approvals from
State, County, and Municipal agencies, as well as working with the owner
to reconfigure an active working site
PROJECT SUMMARY:
TRC Raviv Associates, Inc. (TRC Raviv) performed
environmental investigations of the soil and ground water at this 4-acre
scrap metal recycling facility. Contamination,
which originated from a long history of operations (car crushing began in
1932), includes hydrocarbon related compounds, metals, and PCBs.
The NJDEP ordered the owner to design a system such that continued
operations would not impact the environment, and to address all existing
contamination. The facility
is located in a commercial district, with near-by residences.
TRC Raviv developed the design for a bentonite capping
system (Wyoming bentonite enclosed in a geotextile shell) overlain with
compacted fill. The placement
of this capping system will enable some contaminated soils to be left
on-site, and will ensure that ground water and the underlying soils will
not be further impacted in the future by site operations.
In addition, a storm water treatment system was designed which
includes re-grading of the entire site to collect runoff, a large
detention basin for the settling of particulates, and a 6,000-gallon
oil-water separator. Finally, the site re-development plans include provisions to
improve the visual appearance of the site.
This project was challenging in that it involved
coordination with State, County, and Municipal regulatory agencies to
obtain all of the approvals. In
addition, the remedial solution was designed to be not only cost
effective, but to re-design the site and the operations, such that it
could continue to operate in the future.
The construction will be staged so that the existing operations can
continue during construction.
Back
to Top
3.
LANDFILL CLOSURE - BROWNFIELDS
REDEVELOPMENT
SITE / LOCATION:
Municipal Landfill, Middlesex County, New Jersey
PROJECT HIGHLIGHTS:
- Remedial
investigations of landfill materials, underlying soils, landfill
leachate and gas, ground water, surface water, and sediment
- Obtained
NJDEP approval of remedial action for the complex landfill closure and
site re-development as a shopping center
- Project
design includes filling 10-acres of wetlands, dynamic compaction of
landfill materials, placing 2-million cubic yards of fill, installing a landfill leachate and gas collection
system, and construction of a shopping center with the buildings,
asphalt pavement, and utilities supported by the capping system
PROJECT SUMMARY:
The municipal landfill occupies 60 acres and is
surrounded by wetlands and tidal water bodies.
TRC Raviv Associates, Inc. (TRC Raviv) was retained by the developer to
perform the environmental and civil engineering for the proposed landfill
closure and brownfield redevelopment.
This included extensive environmental and geotechnical
investigations of the landfill materials, soil, ground water, and adjacent
environmentally sensitive areas (i.e., wetlands, surface water).
By combining the environmental and engineering investigations and
designs, TRC Raviv developed a comprehensive redevelopment plan with
substantial cost savings to the client.
TRC Raviv evaluated the environmental and geotechincal
issues associated with future landfill settlement, and leachate migration
and gas generation. To
minimize post-closure settlements, a dynamic compaction program was
designed to consolidate the existing landfill materials.
A compacted stabilized dredge spoil capping system was designed to
ensure the environmentally and structurally sound construction of
buildings, pavement and utilities on the top of the closed landfill.
It was determined that post-closure leachate collection would
likely not be required.
The project received regulatory oversight by several
different bureaus within the NJDEP, and was partially driven by regulatory
permits. TRC Raviv managed the
permit process for the project, and obtained the required permits on
behalf of the client in a timely manner.
By utilizing our environmental, engineering and
regulatory expertise, TRC Raviv obtained NJDEP approval of the Remedial Action
Workplan which included filling 10 acres of adjacent wetlands, capping the
landfill, construction of buildings, pavement and utilities on the capped
landfill, and a short-term leachate and gas collection and treatment
system. When implemented, the
project will have substantial environmental and economic benefits to the
host municipality.
Back
to Top
4.
SPILL/DISCHARGE PREVENTION PLAN - ENGINEERING
AND CONSTRUCTION
SITE / LOCATION: Oil
Refinery, Middlesex County, New Jersey
PROJECT HIGHLIGHTS:
- Evaluated
the existing secondary containment for 20 above ground storage tanks
for compliance with State and Federal regulations pertaining to the
facility Spill and Discharge Prevention Control and Countermeasures (SPCC/DPCC)
Plan
- Tanks
ranged in size from 200,000 to 4,500,000 gallons (5,000 to 110,000
barrels)
- Developed
engineering plans for the upgrade of the secondary containment systems
- Provided
engineering oversight and testing during construction of the upgrades
- Prepared
as-built drawings and amended the SPCC/DPCC Plan
PROJECT SUMMARY:
To maintain compliance with State and Federal
regulations pertaining to the facility Spill/Discharge Prevention Control
and Countermeasures (SPCC/DPCC) Plan, TRC Raviv Associates, Inc. (TRC
Raviv)
evaluated the existing secondary containment for 20 aboveground storage
tanks (ranging in size from 200,000 to 4,500,000 gallons).
Using surveyed site maps, tank information, and site inspections,
tank failure and spill scenarios were evaluated to determine if the
existing secondary containment capacity was adequate.
Additionally, TRC Raviv performed comprehensive engineering evaluations
of containment wall and berm integrity to determine if the existing
containment structures were structurally suitable for spill containment
Based on the evaluations, TRC Raviv developed detailed
engineering plans for the upgrade of all deficient secondary containment
systems. Approximately 10
tanks, with multi-million gallon capacities, required complete upgrades to
their secondary containment systems.
Upgrades included a total reconfiguration of the existing system,
construction of new soil berms, the removal of existing berms to enable a
more effective use of existing containment capacity, reinforcement of
existing concrete containment walls, and sealing of pipe penetration
breaches.
TRC Raviv provided engineering oversight and engineering
testing during the construction of secondary containment system upgrades.
After successful construction, TRC Raviv prepared as-built drawings,
performed final volume calculations to document that the required
secondary containment capacity was achieved, and amended the facility’s
SPCC/DPCC Plan.
Back
to Top
5.
ISRA/RCRA COMPLIANCE - SOIL AND GROUND WATER
REMEDIATION
SITE
/ LOCATION: Paint and Coatings Manufacturing,
Middlesex
County, New Jersey
PROJECT
HIGHLIGHTS:
·
Performed all regulatory compliance activities (ISRA,
RCRA and tank removals) associated with the sale of the facility, and
negotiated with the NJDEP for the elimination of expensive sampling and
monitoring requirements
·
Obtained No Further Action (NFA) determinations for 31 Areas of Concern
·
Implemented aggressive, high vacuum recovery and
treatment of ground water impacted by solvents, primarily toluene
·
Reduced soil disposal costs as part of the underground
storage tank removal program, by implementing in-situ soil vapor
extraction
·
TRC Raviv’s hydrologic assessment obviated the need for more
extensive subsurface investigations
PROJECT SUMMARY:
TRC Raviv Associates, Inc. (TRC Raviv) was retained to conduct the investigation,
removal, and remediation of an underground solvent tank farm.
The creative technique of using Resource Conservation Recovery Act
corrective action management units allowed TRC Raviv to implement a
cost-effective on-site remediation of hazardous waste without applying for
overly burdensome RCRA permits. Soil
was remediated using soil venting and returned to the excavation.
Compliance
with NJDEP’s ISRA program was triggered as a result of the sale of the
facility. All of the required
investigations and the remedial action design were conducted on an
expedited basis. A total of
31 areas of concern were identified and no further action determinations
have been obtained from the NJDEP for all areas except ground water.
TRC Raviv has performed complete turn-key engineering
for the remediation of impacted soil and ground water for this project
including the investigation, design, construction, permitting, and routine
operation and maintenance of a high vacuum, combined ground water and soil
vapor extraction system using a network of over 20 recovery wells. To date, about 600 gallons of organic compounds, primarily
toluene, have been recovered from the subsurface. Ground water contaminant concentrations have been
reduced an average of 85%, and in 3 of 8 key wells the levels have dropped
over 99%. The cleanup of the
ground water and soils is nearly complete and the remediation consists of
“polishing” a few remaining areas.
Based on
research and site-specific hydrogeologic data, TRC Raviv successfully
demonstrated to the NJDEP that a full-scale geophysical investigation was
not warranted at the site. Using
ground water flow and quality data, TRC Raviv demonstrated that the high vacuum
ground water recovery systems exert complete hydraulic control over both
contaminant plumes. This
demonstration eliminated the need to incur additional costs for
geophysical investigations and additional well installation that otherwise
would have been required by the NJDEP.
The original target time frame of the soil and
ground water remediation was 5 years.
However, it is projected that active remediation will be complete
within 4 years. The
regulatory exit strategy for this site includes a monitored natural
attenuation program in conjunction with a deed notice and a capping system
for small amounts of remaining contamination.
Back to Top
6.
UST CLOSURES - GROUND WATER REMEDIATION
PROJECT HIGHLIGHTS
-
Supervision of UST removal and closure of on-site
disposal well
-
Designed, constructed and currently operating a
ground water recovery and treatment system
-
Currently coordinating closure of project in
accordance with Pennsylvania ACT II Requirements
PROJECT SUMMARY
TRC Raviv supervised the
removal of several underground storage tanks and the closure of a disposal
well. A ground water
investigation indicated that elevated levels of volatile organic compounds
were present. As a result,
TRC Raviv implemented a ground water remediation program in 1991.
The remedial design included two ground water recovery wells, an
air stripping tower and an on-site injection well.
During 7 years of ground water remediation,
approximately 75 million gallons of ground water have been treated, and
contaminant concentrations in ground water were significantly reduced.
TRC Raviv is currently coordinating closure of the project in accordance
with the Pennsylvania Department of Environmental Protection's ACT II Requirements.
Back
to Top
7.
SUPERFUND SITE - SOIL AND GROUND WATER REMEDIATION - COST RECOVERY
SITE /
LOCATION: Chemical
Manufacturing/Solvent Recovery Facility, Middlesex
County, New Jersey
PROJECT
HIGHLIGHTS:
·
Site-wide remedial investigation of soil and ground water
·
Horizontal and vertical delineation of DNAPL source area
·
Design and implementation of a Pump and Treat ground
water remediation system involving air stripping with activated carbon
control technology
·
Design and implementation of a treated ground water
recharge basin and injection wells
·
Development of regional ground water flow, and fate and
transport model to optimize remedial action design and predict future
contaminant concentrations of the fugitive, downgradient plume impacting a
major watershed recharge area
PROJECT SUMMARY:
In 1969, the facility began producing and recovering
valuable chemicals from off-site process products and residuals.
In September 1983, the site was listed on the National Priority
List (NPL) with the EPA after volatile organic compounds (VOCs) were
detected in a major potable ground water supply area located hydraulically
downgradient of the site. The
major contaminant of concern, chlorobenzene, was detected in the vicinity
of a production well which prompted immediate remedial action including
the installation of high-yielding recovery wells within the potable well
field recharge area upgradient of the production well to intercept the
dissolved phase VOC plume.
TRC Raviv conducted soil and ground water investigations
that revealed a source area of limited extent.
In one of its first successful applications in New Jersey,
hydropunch sampling was completed at specific depth intervals to delineate
the source area both horizontally and vertically.
Recovery wells were later installed at the areas exhibiting the
highest VOC concentrations.
TRC Raviv demonstrated through pumping tests and pilot
testing that significant cost savings could be achieved by containing the
source area on-site rather than operating high-yielding downgradient
recovery wells. As a result,
a ground water recovery program with on-site treatment was implemented
which reduced the recovery rate and increased the mass recovery of the
VOCs by ten-fold.
TRC Raviv designed a ground water treatment system
consisting of two parallel trains. Components
include state-of-the-art, low profile, easily maintained, air strippers
supplemented by vapor phase activated carbon for reducing air emissions.
The availability of the facility’s on-site steam generation was
utilized to regenerate activated carbon vessels, reducing maintenance
costs. Treated ground water
was injected within a recharge basin with injection wells designed by TRC
Raviv,
upgradient but within the capture zone of the recovery wells to reduce the
discharge limitations.
A ground water flow and fate and transport model were
utilized to show the regulatory agencies that future VOC concentrations
downgradient of the on-site recovery system would degrade before impacting
the potable supply wells. Hence,
ground water recovery from the high-yielding wells downgradient of the
site was terminated, resulting in a significant cost savings for the
company.
Miscellaneous tasks included recovery of costs for
ground water impacts from another Superfund site located hydraulically
upgradient of the site. A
specialized remedial investigation by TRC Raviv revealed compelling evidence
that prompted settlement of the legal case.
Back
to Top
8. MUNICIPAL LANDFILL GROUND WATER INVESTIGATION
LOCATION: Ocean
County, New Jersey
PROJECT HIGHLIGHTS:
·
Streamlined the investigation of a closed municipal
landfill by combining the SI and the RI into one phase and by employing
real-time delineation techniques. Used
landfill leachate indicator parameters to identify contaminant migration
pathways
·
Negotiated work plans with the NJDEP under the scrutiny of
several interested parties, including a citizen-led group formed to
explore potential causes of childhood cancer cases and the NJDHSS
·
Analyzed 15 years of historical ground water quality data to
establish temporal trends and evaluate contaminant plume stability over
time, and refute inaccurate statements about off-site impacts
·
Presented findings at several public meetings of concerned
citizen group
·
Supported arguments for natural remediation of the minimal
landfill impacts to ground water quality that were identified
·
Developed scientifically based, cost effective long-term
monitoring program to confirm plume stability and natural remediation
processes
PROJECT SUMMARY:
TRC Raviv Associates, Inc.
(TRC Raviv) was retained by a Township in Ocean County to satisfy the
requirements of a Memorandum of Agreement (MOA) that was entered into by
the Township with the New Jersey Department of Environmental Protection (NJDEP).
The MOA required the investigation of a municipal solid waste
landfill that had been closed. The landfill was being investigated as one of several
potential sources of carcinogens in an effort by a citizen's
group and state agencies to identify potential causes of childhood
cancers.
The MOA required that the
Township complete a Preliminary Assessment, prepare a Site Investigation
Workplan, implement the Site Investigation and prepare a report, and
prepare a Remedial Investigation Workplan, implement the Remedial
Investigation and prepare a report.
TRC Raviv
saved at least a year and several tens of thousands of dollars by
combining the Site Investigation and Remedial Investigation, thereby
eliminating the need for at least one workplan and report, with all the
concomitant time frames for preparation, client review, and review by the
NJDEP. By fully assessing and
utilizing the historical information compiled in the Preliminary
Assessment, we were able to focus the Site Investigation/Remedial
Investigation on just those Areas of Concern (AOCs) that truly warranted
investigation, thereby keeping the scope of the investigation
appropriately focused.
During the initial phase
of the Remedial Investigation, TRC Raviv employed real-time delineation
techniques - Hydropunch ground water sampling and field analysis for
landfill leachate indicator parameters - to delineate ground water quality
impacts. This provided data
to scientifically select locations for permanent monitoring wells and
minimize the number of iterative phases of well installation.
TRC Raviv worked in conjunction with ground water modelers who were
developing a 3-dimensional regional flow model for a Superfund site 2
miles to the west; this model assisted us in the determination of
contaminant migration pathways and the selection of monitoring well
locations.
TRC Raviv represented the Township at negotiations with the
NJDEP at which key elements of the Remedial Investigation were negotiated,
and made several presentations at the monthly meetings held by the group
of concerned citizens investigating possible causes of childhood cancer in
the Township. These meetings
are regularly attended by 100 to 200 citizens and representatives of
local, state and federal agencies.
Back
to Top
9.
SEDIMENT ENCAPSULATION - ENGINEERING AND CONSTRUCTION
SITE / LOCATION:
Dundee Canal, Passaic County, New Jersey
PROJECT HIGHLIGHTS:
- Environmental
investigation of soil, sediment, surface water quality, and hydraulic
connection between canal and ground water
- NJDEP
approval of remedial action workplan for subaqueous in-place capping
of impacted sediment
- Full-service
engineering including geotechnical evaluation of canal sediment,
capping system design, bid procurement/contractor selection,
permitting, construction management, as-built drawings, Remedial
Action Report and Deed Notice
- Installation of a 3.5-acre capping system for 9,000
cubic yards of impacted sediment
- $1.2 million remedial action design, installation,
and reporting completed within budget
PROJECT SUMMARY:
The Dundee Canal ran parallel to the Passaic River
extending over a mile from the Dundee Dam in Clifton, New Jersey to its
outlet at the Passaic River in Passaic, New Jersey.
The Canal was partially filled as a result of the New Jersey
Department of Transportation construction of the Route 21 extension, but
two unfilled portions or ponds covering an area of 3.5 acres remained.
TRC Raviv Associates, Inc. (TRC Raviv) performed remedial
investigations of canal soil, sediment and surface water to delineate the
extent of contaminants in the Canal and to assess the hydraulic connection
between the Canal and ground water.
TRC Raviv
designed a 3.5-acre in-place capping system for the ponds to ensure
containment of 9,000 cubic yards of sediment and facilitate the natural
re-establishment of the aquatic ecosystem.
The plan was approved by the NJDEP.
The sediment
was 15 feet thick in locations and had very low strength. TRC Raviv performed a detailed geotechnical-testing program that
enabled the selection of a permeable geotextile with a permeable soil
cover that successfully contained the sediment while supporting the weight
of the cap. The final capping
system design included an anchored geotextile overlain by 2 feet of fill.
The fill was specifically selected to resist erosion once the pond
areas were refilled with flowing water and to facilitate the
re-establishment of the aquatic ecosystem after encapsulation.
The 3.5-acre capping system was installed under the
direct supervision of TRC Raviv engineers.
The capping system installation was successfully completed, within
budget, in June 2000. TRC
Raviv
prepared the Remedial Action Report, which included as-built drawings and
the draft Deed Notice, for submittal to the NJDEP.
Back
to Top
10.
GROUND WATER SUPPLY
SITE
/ LOCATION:
Senior Retirement Community, Morris County, New Jersey
PROJECT
HIGHLIGHTS:
·
Implemented several single-well and two multi-well
aquifer pumping tests to determine well and aquifer yields
·
Calculated basin water budget and aquifer recharge rates
to support ground water withdrawal needed by development
·
Prepared and obtained NJDEP approval to modify
Township’s existing Water Allocation Permit to include the new
development’s ground water supply wells
PROJECT
SUMMARY:
TRC Raviv Associates, Inc. (TRC Raviv) was retained by a major residential
developer in northern New Jersey to implement an aquifer-testing program
at a senior retirement community under construction in Morris County, New
Jersey. Due to shortages in
the host Township’s existing ground water supply system, the developer
was required to identify and develop sufficient water to meet the planned
community’s needs. To that end, the developer installed eight test wells
into the crystalline bedrock underlying the site. Once the developer could
develop sufficient yield, the wells were to be tied into the Township’s
existing water supply and distribution system.
The
community needs about 120,000 gallon per day (gpd), equivalent to an
average of about 85 gallons per minute (gpm). In accordance with the New
Jersey Department of Environmental Protection-Bureau of Safe Drinking
Water (NJDEP-BSDW), the developer had to demonstrate that the new wells
had the capability of providing more than three times the needed yield, to
ensure adequate supply if any individual well fails to supply an adequate
yield, or if one of the Township’s wells temporarily goes off-line.
TRC Raviv
designed a ground water well and aquifer testing program to satisfy the
requirements of the NJDEP-Bureau of Water Allocation (BWA).
Initially, step tests were run on each individual well to determine
the maximum sustained yield. After
the optimal pumping rate was selected, a 72-hour pumping test was run on
each well to verify that the well could provide the yield on a sustained
basis. Transducers were
installed in nearby wells to provide water-level data to assess aquifer
properties and interference effects.
A multi-well aquifer pumping test work plan was provided to the
NJDEP-BWA for their approval. Through our close working relationship with this bureau, we
were able to address their concerns and obtained timely approval for the
client.
A
72-hour, five-well aquifer pumping test was conducted to verify that the
aquifer could sustain a withdrawal rate of 270 gpm. TRC Raviv coordinated with a pumping-test contractor to provide
pumps and flow measurement equipment; we installed transducers in pumping
and observation wells that recorded water-level data electronically.
Water-level measurements were also collected in piezometers in
on-site wetlands to show that pumping the bedrock aquifer would not have
an adverse effect on wetlands habitats.
The water-level data were processed using computer-driven programs
to determine aquifer hydraulic properties and demonstrate long-term
aquifer yield.
TRC Raviv
calculated a water budget for the entire drainage basin and determined the
safe yield of the well filed in accordance with NJDEP requirements.
We used the results of the testing program to prepare a
comprehensive hydrogeologic report and an application to modify the
Township’s existing Water Allocation Permit to incorporate the
community’s new wells and increase the overall allocated pumpage. We received high praise from the NJDEP-BWA for the
completeness and scientific quality of the two documents, and the request
for modification has been granted by the NJDEP.
Back
to Top
11.
ISRA COMPLIANCE - SOIL AND GROUND WATER INVESTIGATIONS AND REMEDIATION
SITE / LOCATION: Chemical
Manufacturing Facility, Bergen County, New Jersey
PROJECT
HIGHLIGHTS:
·
Site-wide remedial investigation of soil and ground water
·
Horizontal and vertical delineation of LNAPL source area
·
Excavation of impacted soils in an active loading dock
area
·
Design, implementation and operation of a bioremediation
pilot testing program for treating volatile organic compounds in ground
water
·
Design of a bioremediation system for ground water
remediation
·
ISRA compliance following a transfer of company assets
PROJECT SUMMARY:
The facility, located in an industrial area of Bergen
County, New Jersey, began producing vinyl-type coatings in 1969, and later
added fabric softeners to the product line.
Raw materials included alcohols, pigments and phthalates.
Following the removal of underground storage tanks (USTs),
the major contaminants of concern detected in soil and ground water at the
site were isopropyl alcohol (IPA), acetone (a degradation product of IPA),
and phthalates. Monitoring
wells revealed impacts to the overburden and bedrock wells.
The extent of the plume was limited to the property due to gentle
ground water gradients and natural degradation of the contaminants.
TRC Raviv Associates, Inc. (TRC Raviv) delineated the
dissolved plume horizontally and vertically, and identified the transfer
lines from the former USTs as one of the contaminant sources.
Observations of impacted soils during the removal of the transfer
lines confirmed that contaminant releases were associated with the lines.
A bench-scale biodegradation study was conducted to determine the
feasibility of bioremediation of the compounds of concern.
The study indicated that bioremediation was a viable option.
The severely impacted soils were excavated over a
holiday period during temporary cessation of facility operations.
The excavation was extended to the top of bedrock.
The area was backfilled with a permeable medium and three
bioreactor trenches were installed for implementation of a bioremediation
system. A bioremediation
pilot study was conducted, introducing a passive oxygen releasing compound
(ORC) within the bioreactor trenches and later liquid nitrogen and
phosphorous as nutrients. These
compounds had been identified as the limiting compounds for bioreaction
processes. The results of
this pilot study indicated that bioremediation was successfully enhanced,
rapidly reducing the contaminant concentrations in ground water.
This information was utilized in the design of a more aggressive,
permanent, low cost bioremediation system.
The bioreactor trenches installed following soil excavation will
deliver the oxygen and nutrients to the contaminated ground water.
Subsequently, the facility’s assets (building and
equipment) were purchased, which triggered ISRA compliance. TRC Raviv was retained to inspect the premises and complete a
preliminary assessment report and site investigation in other areas of
concern.
Several additional miscellaneous tasks were completed
by TRC Raviv including engineering design and construction oversight of a
secondary containment structure for off-loading raw materials in the
loading dock area.
Back
to Top
12.
ISRA COMPLIANCE - SOIL AND GROUND WATER INVESTIGATIONS - PRODUCT RECOVERY
SITE / LOCATION:
Freon Manufacturing
Facility, Bergen County, New Jersey
PROJECT HIGHLIGHTS:
·
Successfully completed
complex delineation of 13 areas of concern (AOCs)
·
Identified and
delineated several dense non-aqueous phase liquid (DNAPL) area
·
Removed over 1,000
gallons of DNAPL from the ground water within 3 weeks of discovery
·
The quick response to
DNAPL recovery improved ground water quality, resulting in significant
long-term cost savings to the client
PROJECT
SUMMARY:
TRC Raviv conducted supplemental soil and ground water
investigations at the site for compliance with ISRA. TRC Raviv reviewed the prior consultant’s work and prepared a
soil and ground water Remedial Investigation Workplan for submittal to the
NJDEP that identified potential AOCs and suspected dense non-aqueous phase
liquid (DNAPL) areas.
The NJDEP-approved workplan
consisted of soil sampling, ground water sampling, a Geoprobe ground water
investigation and monitoring well installation.
The results of soil sampling confirmed the extent of elevated
levels of volatile organic compounds, base neutral compounds, metals and
PCBs. The presence of DNAPL,
consisting of freon and other chlorinated hydrocarbons, was confirmed in
several areas. TRC Raviv
immediately began product recovery activities and removed over 1,000
gallons of DNAPL within 3 weeks of discovery. Subsequent DNAPL delineation investigations revealed the
presence of DNAPL within the thin sand layers of the site’s underlying
varved clay. TRC Raviv designed a
network of recovery wells to intersect the DNAPL zones and continue DNAPL
recovery.
TRC Raviv
is currently evaluating remedial technologies for ground water including
Hydrogen Release Compound, Vacuum-Enhanced Recovery and Funnel and Gate
Treatment/Containment. For soil remediation, an On-Site Thermal Desorption
Unit is being considered.
Back to Top
13.
ISRA COMPLIANCE - SOIL AND GROUND WATER REMEDIATION
SITE / LOCATION:
Petroleum Products
Manufacturing, Middlesex County, New Jersey
PROJECT HIGHLIGHTS:
·
Coordination of all ISRA Compliance Activities
·
Supervision of Site-Wide Decommissioning Activities
during Demolition
·
Implementation of Soil and Ground Water Remedial
Investigations
·
NJDEP and USEPA Approval of Site-Wide Cap for
PCB-Impacted Soils
·
NJDEP Approval of a Site-Specific Ecologically-Based
Alternate Cleanup Level for PCBs in On-Site Wetlands
·
Design and Operation of a Vacuum-Enhanced Product
Recovery System
PROJECT SUMMARY:
TRC Raviv assisted with the closure of a 15-acre
industrial establishment that had been in operation since 1903. The site consisted of 20 buildings used for the manufacture
of petroleum jelly and other associated products.
TRC Raviv implemented the required ISRA compliance activities including
the Preliminary Assessment Report, Remedial Investigation Reports, and
Soil and Ground Water Remedial Action Workplans.
TRC Raviv conducted the necessary remedial activities
during the razing of the plant, including the removal of numerous
underground and above ground storage tanks.
Many other areas of concern (AOCs) such as oil/water separators,
sumps and pipelines were decommissioned, removed and sampled during the
demolition of the facility. Implementation
of these remedial tasks at this time resulted in significant cost savings
to the client.
Comprehensive site-wide soil and ground water
investigations were performed by TRC Raviv, and
contaminants such as base neutral compounds (BNs), heavy metals,
PCBs, petroleum jelly, and volatile organic compounds (VOCs) were detected
at elevated concentrations.
TRC Raviv
successfully demonstrated to the NJDEP that (1) all metals and BNs were
attributable to historic fill material; (2) petroleum jelly was a
non-hazardous substance; and (3) PCBs were not impacting ground water.
Following negotiations with the USEPA, NJDEP, and
prospective purchaser, a site-wide cap and deed notice were approved as
remedial measures to address PCBs in soil.
The NJDEP also approved the excavation of off-site PCB-impacted
soils for placement under the on-site cap, which resulted in a significant
cost savings to the client. Another
cost-saving measure included successful negotiations with the host
municipality resulting in off-site institutional and engineering controls
on city-owned property.
TRC Raviv prepared the bid specifications, soil erosion
and sediment control plan, and permit applications for the soil excavation
work and assisted the client in selecting a contractor.
We also provided full-time field supervision of the soil excavation
project.
TRC Raviv performed a comprehensive Ecological Evaluation
and proposed a Site-Specific Ecologically-Based Cleanup Level for PCBs in
on-site wetlands. The NJDEP
approved of a less stringent Alternate Cleanup Level, resulting in
significant cost savings since wetlands remediation and restoration were
not required.
To address ground water,
TRC Raviv conducted an investigation to determine the extent and source of
floating petroleum product. The
product was delineated and a recovery system was designed using a high
vacuum to remove the light non-aqueous phase
liquid (LNAPL).
Recovered LNAPL and ground water are separated using an
oil/water separator. Water is
treated with clay filters and granular activated carbon and discharged to the sanitary sewer.
The system is maintained and operated by TRC Raviv's New Jersey-licensed wastewater treatment plant
operators, who perform routine sampling and reporting to comply with air
and water discharge permits.
Back to Top
14.
ISRA COMPLIANCE - SOIL AND GROUND WATER INVESTIGATIONS - SOIL REMEDIATION
SITE /
LOCATION: Wood Treating Facility, Burlington County, New Jersey
PROJECT HIGHLIGHTS:
·
Coordination of ISRA Compliance Activities
·
Successfully completed delineation of 9 areas of concern
(AOCs).
·
Implementation of Soil and Ground Water Remedial
Investigations
·
Engineering Design of NJDEP-Approved Site Cap for
Arsenic-Impacted Soils
·
Provided Engineering Inspections of the Implementation of
the Capping System
PROJECT SUMMARY:
Soil and ground water
investigations were performed at the 13-acre wood treating facility in
southern New Jersey for compliance with ISRA.
Reporting activities included the Preliminary Assessment Report,
Remedial Investigation Workplans and Reports, and a Soil Remedial Action
Workplan.
As a result of the initial
soil sampling program, TRC Raviv determined that arsenic was the primary
contaminant of concern at the site and the NJDEP agreed to limit future
sampling to arsenic analysis only.
TRC Raviv
successfully demonstrated to the NJDEP that the contaminated soils could
be capped in place on-site, in conjunction with other site improvements
(i.e. paving) planned by the property owner.
TRC Raviv prepared
the bid specifications for the soil excavation activities and assisted the
client in selecting a contractor to perform the work.
Our engineers provided full-time field supervision of the
arsenic-impacted soil excavation and capping project. In accordance with
an NJDEP-approved Soil Remedial Action Workplan, approximately 8,000 cubic
yards of arsenic-impacted soil were excavated, relocated, and capped with
asphalt, resulting in significantly reduced costs and future liability to
the client. The project took
approximately 6 weeks and $1,000,000 to complete.
TRC Raviv proposed to conduct quarterly ground water
sampling to demonstrate that elevated levels of ammonia and nitrate in
ground water are undergoing natural attenuation.
This passive form of remediation has resulted in significant
savings to the client.
Back
to Top
15.
ISRA COMPLIANCE - SOIL REMEDIATION - GROUND WATER INVESTIGATION
SITE
/ LOCATION: Petroleum Research and Development
Center, Mercer County, New Jersey
PROJECT
HIGHLIGHTS:
·120
areas of concern have received No Further Action determinations
·Site-wide multimedia investigation of
soil, ground water, surface water and sediments
·Active
participation in marketing of property leading to eventual sale
·Investigation
of chlorinated solvents in fractured bedrock
·Implementation
of low-temperature thermal desorption for VOC-impacted soils
·Natural
attenuation of ground water with the establishment of a CEA proposed
·Preparation
of a Baseline Ecological Evaluation
PROJECT
SUMMARY:
The 440-acre site
consisted of 20 buildings primarily engaged in research and development
activities related to petroleum processing, energy conversion, and
catalysis. TRC Raviv prepared a
Preliminary Assessment Report that identified approximately 130 areas of
concern. Several phases of
investigative work were conducted by TRC Raviv in accordance with the NJDEP’s
Technical Requirements for Site Remediation without formal NJDEP
workplan approval to assess the environmental conditions at the site in
anticipation of a sale of the property, and to expedite the ISRA
compliance process. As a result, our project team was able to accurately present
the environmental quality and regulatory status of the facility to
prospective purchasers.
Throughout the ISRA compliance process, TRC Raviv worked
closely with the seller’s Global Real Estate Team to market the
property. TRC Raviv was
responsible for presenting the environmental conditions of the site and
explaining the nuances of the ISRA compliance process to a variety of
potential buyers, their consultants, real estate brokers and attorneys.
Numerous site inspections and meetings were conducted.
TRC Raviv was instrumental in working with purchasers and their
consultants who were seriously considering purchasing the property to
satisfy due diligence requirements. The
property was eventually sold in a timely manner prior to the completion of
ISRA compliance.
One of the soil issues at the site was the
persistent detection of beryllium in sediment and soil samples. To address this problem, TRC Raviv conducted a background
investigation followed by a statistical analysis of the data to determine
whether there was a statistical difference between on-site and background
data sets. The statistical
results indicated that the beryllium detected in on-site soils were
naturally occurring. The
NJDEP agreed, and no further investigation or remediation of elevated
levels of beryllium was required.
To address soils below
a drum storage pad contaminated with chlorinated solvents, TRC Raviv evaluated
several remedial alternatives and selected on-site treatment via
low-temperature thermal desorption. The
low-temperature thermal desorption system utilized ex-situ steam stripping
for the remediation of volatile organic compounds.
The process involved loading the contaminated soil into two steel
treatment processors in 10-ton batches.
The time required to process each batch of soil was approximately 4
hours, as determined during a bench scale treatability study.
A total of 77 tons of soil was remediated in this manner.
The NJDEP issued a No Further Action Letter upon its completion.
The low-temperature thermal desorption process was both
cost-effective (approximately 50% less than disposal) and timely
TRC Raviv prepared a Baseline Ecological Evaluation to
evaluate potential adverse ecological impacts using site-specific data
collected from on-site Environmentally Sensitive Areas and areas of
concern. Based on the
comparison of the contaminant concentrations to ecological screening
criteria, TRC Raviv determined that the potential for contaminants of potential
ecological concern to adversely affect biota were minimal.
No further ecological evaluation was proposed to the NJDEP.
Following an initial ground water investigation at
eight Areas of Concern, ten clusters of monitoring wells were installed in
the overburden and bedrock aquifers at the site.
Additional wells were installed to horizontally and vertically
delineate dissolved volatile organic compound contamination. TRC Raviv calculated the fate and transport of three separate
volatile organic compound plumes and presented a natural ground water
remediation proposal with the establishment of a Classification Exception
Area (CEA) to the NJDEP. Quarterly
ground water monitoring has demonstrated that the concentrations are
decreasing over time and confirmed the predicted fate and transport of the
volatile organic compounds.
Back
to Top
16.
BROWNFIELDS REDEVELOPMENT - DNAPL (COAL TAR PRODUCT) RECOVERY
- CLASS IIIB AQUIFER DESIGNATION - NJPDES PERMITTING - COST RECOVERY
SITE / LOCATION:
Former Manufactured Gas Plant, Hudson County, New Jersey
PROJECT
HIGHLIGHTS:
·
Site-wide remedial investigation of soil and ground water
·
Horizontal and vertical delineation of DNAPL source area
·
Design and implementation of coal tar recovery pilot
testing program involving a unique methodology of product upwelling
·
Design, implementation and operation of a coal tar
recovery system for an interim remedial measure (IRM)
·
Determination of a Class IIIB aquifer designation for
on-site saline water-bearing zones for development of site-specific,
alternative ground water quality criteria
PROJECT SUMMARY:
The 300-acre property is located along the western
shore of the Hudson River at its confluence with Upper New York Harbor.
Historically, the property was occupied by a former coal
gasification or manufactured gas plant (MGP site), rail yards, warehousing
and shipping docks, and in later years, a former gasoline service station.
The current shoreline of the property has been created by historic
backfilling; much of the property was below water prior to filling
activities in the first half of the 20th century.
Contaminants detected at the site include historic fill with
elevated base neutrals (including polynuclear aromatic hydrocarbons [PAHs]
and metals); coal tar product from the MGP; and petroleum-based
constituents from the former service station and other historic operations
on the property.
In the early 1980s, the barren property was
recognized as a potential site for commercial and residential
redevelopment. Today, despite
the historic contamination, creative remedial measures have been
implemented allowing redevelopment to go forward.
Currently, the property includes a major regional shopping mall,
office centers and high-income residential communities, and is one of the
largest brownfields projects ever undertaken in New Jersey.
TRC Raviv Associates, Inc. (TRC Raviv) has been involved
with the project since the early planning phases of the redevelopment.
Initially, swift and comprehensive soil and ground water
investigations were conducted in high priority areas prior to construction
of infrastructure and buildings. Several
areas required prompt remedial action prior to construction activities,
including removal of a former subsurface gasholder containing liquid coal
tar and a bioremediation system beneath the foundation of a major store.
More recent remedial efforts have focused on the coal
tar product plume, which is the primary source of dissolved contamination
in ground water. Investigations
have revealed two areas containing coal tar product in both residual and
free product phases. The
extent of the coal tar product has been delineated horizontally and
vertically within the complex lithology.
Coal tar recovery pilot testing has taken advantage of a unique
methodology. The major coal
tar plume consists of a DNAPL with a specific gravity similar to seawater,
which is known to upwell in areas where excessive ground water pumping (in
water supply wells) occurs. The
pilot testing induced coal tar flow, creating an upwelling of product in a
well by reducing the water table elevation with a separate pump.
The pilot testing results indicated that coal tar recovery could be
increased by more than an order of magnitude when induced pumping was
employed. The dissolved phase
contamination in ground water was also delineated to reveal potential
discharge points.
The latest focus of TRC Raviv’s remedial investigation
has involved the evaluation of the natural contamination of the
water-bearing zones by saline waters of the Hudson River and potential
pathways to the sensitive receptor, the Hudson River.
Inexpensive analytical tests were included with the site-wide
sampling events to delineate the non-potable saline ground waters at the
site. Remedial investigation programs were tailored to evaluate
potential contaminant migration pathways including subsurface utilities
that transect the site, and direct ground water discharge to the Hudson
River. The results of this
latest remedial investigation satisfied requirements for a Class IIIB
aquifer designation proposal. The
Class IIIB aquifer designation will allow for development of
site-specific, alternative remedial standards that will result in
substantial cost savings in the remedial action effort.
An IRM remedial action has been installed and
operating continuously for more than two years, recovering coal tar free
product from the major coal tar plume.
Current remedial efforts include the design of a more aggressive
coal tar recovery system and development of Class IIIB site-specific,
alternative remedial standards.
On-going miscellaneous tasks conducted by TRC Raviv at the
site include NJPDES “discharge to surface water” permitting for
construction dewatering activities and supervision of construction
activities for compliance with a site-wide remedial plan.
Back
to Top
17. SECONDARY
CONTAINMENT AREA - ENGINEERING
SITE: Manufacturing
Facility, Carlstadt, New Jersey
PROJECT HIGHLIGHTS:
- Design and construction of a secondary containment
area for trucking operations to comply with NJDEP Discharge
Prevention, Containment and Countermeasures (DPCC) requirements.
PROJECT SUMMARY:
TRC Raviv Associates, Inc. (TRC Raviv) performed the design
and construction inspection of a secondary containment system to meet
NJDEP DPCC requirements. Our
client sold the manufacturing facility and, as a condition of the sale,
was required to install a secondary containment area for tanker trucks
which deliver chemicals to outdoor, aboveground storage tanks.
Under the constraints of limited available space and heavy routine
trucking operations, TRC Raviv developed a cost-effective design that provides
the necessary containment (6,000 gallons) without limiting access to
routine heavy truck traffic. Additionally,
by working closely with the construction contractor during the design
stages, TRC Raviv expedited the design and construction so that the containment
area could be installed on budget and within the short timeframe required
by the NJDEP.
Back
to Top
18.
RCRA CORRECTIVE ACTION - FACILITY INVESTIGATION
SITE
/ LOCATION:
Former Chemical Plant, Guayanilla, Puerto Rico
PROJECT
HIGHLIGHTS:
·
Implemented Supplemental RFI in Puerto Rico directing a
multi-company team of Puerto Rican and U.S. scientists at former chemical
plant and surrounding community
·
Negotiated deferral of USEPA requirement for active pump
and treat Interim Remedial Measure. Instead
collected and evaluated data in accordance with the most recent USEPA
protocols to support natural remediation remedy for chlorinated VOCs
·
Coordinated bench-scale studies of natural and enhanced
biodegradation processes with research group at Carnegie Mellon Research
Institute to assess cost-effective remedial options to address
site-specific conditions
·
Carried out bilingual communications with federal and
Puerto Rico agency representatives to implement site activities and
address regulatory concerns
·
Obtained permits and approvals from Puerto Rico
regulatory agency for discharge of waters generated during well
installation and ground water sampling
PROJECT
SUMMARY:
TRC Raviv Associates, Inc. (TRC Raviv) was retained in 1996 by a major chemical
company to assume responsibility for an on-going RCRA Facility Assessment
on the south coast of Puerto Rico. Operations
at the site were discontinued in 1978, followed by an extensive voluntary
cleanup of contamination. The
client entered into a RCRA 3008(h) Administrative Order in 1990 and
conducted the first phase of the RCRA Facility Assessment from 1991 to
1995.
The
former plant has been ranked as a high priority site under the USEPA’s
RCRA corrective Action program.
TRC Raviv
assisted the client in responding to the USEPA’s requirements for a
supplemental RCRA Facility Assessment and an Interim Measure.
Utilizing the TRC Raviv Senior Project Manager’s 7-year his |